A 10×20 shed material list for a gable shed on skids is 154 2x4s (121 for framing), 25 treated 2x6s, 8 treated 4x4s, 8 sheets of 3/4 in plywood, 11 of OSB, 19 of T1-11 and 11 shingle bundles, for 94 1/2 in walls, a 6/12 roof and 12 in eaves.
Every quantity and cut length on this page comes from the shopping list, cut list and cutting plan in the 3DSHEDPLANS 10×20 gable shed plan PDF (74 pages, 28 sections), which the plan estimates at about 80 hours for two people. The list counts what to buy by stock length, and the plan checks splices, header depth and sheet coverage. It is drawn with one 72 in double door, two 36 x 36 in windows and a detachable ramp.
What this 10×20 shed material list assumes
The plan is a gable shed 10 ft deep and 20 ft wide, with 200 sq ft of floor and the ridge running the 20 ft way. These are its settings:
- Walls: 94 1/2 in tall including the bottom plate and double top plate, so wall studs are cut to 90 in (7′ 6″).
- Spacing: studs, floor joists and rafters all at 16 in on center.
- Roof: 6/12 pitch, 2×4 rafters, a 2×6 ridge board, 12 in eave overhang and 4 in rake overhang. The roof footprint is 20′ 9 1/2″ by 12′ 1 1/2″.
- Floor: four pressure-treated 4×4 skids 20 ft long, about 39 in apart (38.8 in), on a crushed stone pad 22′ 0″ x 12′ 0″ and 4 in deep in a pressure-treated 4×6 frame (frame diagonals 25′ 0 3/4″, plus an 8′ 9″ wide landing in front of the door; layout diagonals 22′ 4 5/16″), with 2×6 joists cut to 9′ 9″ at 16 in on center and 3/4 in tongue and groove plywood.
- Loads: the 2×4 rafters were checked at 30 psf ground snow (SPF #2 at 16 in, 60 in run). That is the plan’s design assumption; if your area’s snow load may be higher, check your local permit office before you buy rafter stock.
- Openings: a 72 in wide double door (76 1/2 in rough opening height) centered in the 20 ft front wall, from 7′ 0″ to 13′ 0″ measured from the left corner, and two windows, each a 36 x 36 in rough opening with the sill 3′ 6″ above the bottom plate, one in each 10 ft gable wall. The back wall has no openings.
- Heights: the floor sits 9 3/4 in above the ground, the walls top out at 8′ 8 1/4″ and the peak at 11′ 5 5/16″. The door has 6′ 5 1/4″ of clear height under the head stop.
- Ramp: a detachable pressure-treated ramp, 6′ 9″ wide and 3′ 6″ out from the door, at a 1:6 slope.
- Time: the plan estimates about 80 hours for two people: 7 for the site and foundation, 8 for the floor, 20 for the walls, 13 for roof framing, 17 for sheathing and shingles and 15 for the door, windows, trim, ramp and paint.
Our 10×20 gable shed plan is this exact build: the re-issued PDF prints the same shopping list, cut list and cutting plan, so you can shop from this page or from the plan.
Shopping list by stage
Lumber sizes are nominal. A 2×4 measures about 1 1/2 x 3 1/2 in, as the American Wood Council explains. Check the grade stamp on plywood and OSB; the APA trademark guide shows how to read it.
Totals at a glance
| Material | Total |
|---|---|
| 2×4 boards, all lengths (121 framing, 3 seam blocks, 30 for braces, post, stakes and cleats) | 154 |
| Pressure-treated 2×6 (17 joists, 4 for the two rims, 4 for the ramp) | 25 |
| Pressure-treated 4×4 (one 8 ft and one 12 ft per 20 ft skid) | 8 |
| Pressure-treated 4×6 (pad frame) | 7 |
| Pressure-treated 2×4 (skid splice scabs, ramp ledger) | 4 |
| Pressure-treated 2×10 x 8 ft (ramp stringers) | 2 |
| 2×6 (ridge and window headers) | 4 |
| 2×8 x 14 ft (door header) | 1 |
| 3/4 in T&G plywood sheets (floor) | 8 |
| 7/16 in OSB sheets (roof) | 11 |
| 5/8 in T1-11 sheets (walls, gables, door leaves) | 19 |
| 1/2 in plywood sheets (soffit, header fillers) | 2 |
| 3-tab shingle bundles | 11 |
Foundation and floor
| Item | Qty | Used for |
|---|---|---|
| Pressure-treated 4×4 x 8 ft, tagged for ground contact | 4 | One piece of each 20′ 0″ skid |
| Pressure-treated 4×4 x 12 ft, tagged for ground contact | 4 | The other piece of each skid |
| Pressure-treated 2×4 x 14 ft | 2 | Eight 3′ 0″ splice scabs, one on each side of each skid joint |
| Pressure-treated 2×6 x 10 ft | 19 | 17 floor joists cut to 9′ 9″, including a second joist at the rim joint, and the 112 3/4 in rim pieces |
| Pressure-treated 2×6 x 12 ft | 2 | Rim pieces cut 127 1/4 in (two 20′ 0″ rim joists in all) |
| 3/4 in T&G plywood, 4×8 sheet | 8 | Floor decking (200 sq ft) |
| 2×4 x 8 ft | 3 | Flat blocks under the decking seams |
| Crushed stone 3/4 in, loose | 4.7 cu yd | Gravel pad, measured loose before tamping |
| Pressure-treated 4×6 x 16 ft, ground contact | 4 | Pad frame |
| Pressure-treated 4×6 x 12 ft, ground contact | 2 | Pad frame |
| Pressure-treated 4×6 x 8 ft, ground contact | 1 | Pad frame |
| Rebar stakes 1/2 in x 24 in | 32 | Pad frame |
| Galvanized timber spikes 3/8 x 10 in | 16 | Pad frame corners |
| Deck screws 2 in (or 6d ring-shank nails), rated for treated lumber | 5 lb | Decking |
| Construction adhesive, 10 oz tube | 10 | Joist, rim and door-frame beads |
| Ground anchors, screw-in auger type, 30 in or longer, with straps | 8 | Anchoring the two outside skids |
| Structural wood screws 1 1/2 in, exterior | 48 | Anchor straps |
Walls and roof framing
| Item | Qty | Used for |
|---|---|---|
| 2×4 x 8 ft | 63 | 52 wall studs, cripples, window sills, short plate pieces, gable studs, center gable studs, ridge splice cleat |
| 2×4 x 10 ft | 15 | Side wall plates and cap plates, back plate pieces, collar ties, frieze blocks |
| 2×4 x 12 ft | 17 | 14 rafter ties, back plate pieces, gable vent sills and headers |
| 2×4 x 14 ft | 25 | 32 rafters and 4 fly rafters (two per board), front plate and cap plate pieces, door and window trimmers |
| 2×4 x 16 ft | 1 | Back cap plate |
| 2×6 x 8 ft | 2 | Window headers (one board per window) |
| 2×6 x 10 ft and 12 ft | 1 + 1 | Ridge board (20′ 8″, spliced) |
| 2×8 x 14 ft | 1 | Door header (two 6′ 3″ pieces) |
| Hurricane ties, H2.5A type or equal | 28 | Rafter to plate |
| Framing angles, A34 type or equal | 4 | End rafters at the 4 corners |
| Temporary braces 2×4 x 12 ft | 18 + 4 | Plumb braces and a squaring diagonal per wall section, plus 4 for the center gable studs, reused later |
| Temporary ridge post 2×4 x 12 ft | 1 | Under the ridge joint until that rafter pair is set |
| 2×4 x 8 ft | 4 | 12 pointed brace stakes, 24 in each |
| 2×4 x 8 ft | 3 | 16 deck cleats, 12 in each, for the braces and the center gable studs |
The three header filler strips of 1/2 in plywood are ripped from a soffit sheet, so buy the soffit plywood with the wall lumber. The 121 framing boards, the 3 seam-block boards and the 30 boards for braces, post, stakes and cleats put 154 2x4s on the truck. The plan adds that you should buy 2 or 3 spare studs for bad boards.
Roof covering
| Item | Qty | Used for |
|---|---|---|
| 7/16 in OSB, 4×8 sheet | 11 | Roof sheathing |
| 15 lb felt, 400 sq ft roll | 1 | Underlayment |
| 3-tab shingles, 26 per bundle | 11 bundles | Roof, starter course and ridge cap |
| Drip edge, 10 ft | 10 | Eaves and rakes |
| Roofing nails 1 1/4 in galvanized | 9 lb | Shingles |
| Roofing cap nails 1 in | 2 lb | Felt |
| Roofing cement, 10 oz tube | 2 | Roofing |
| Louvered gable vent, 12 x 12 in | 2 | One in each gable |
| Under-eave vent 16 x 8 in, screened | 8 | Air in under the eaves, 4 under each eave |
| Insect screen, 2 ft x 25 ft | 1 roll | Vent holes and gaps at the eaves |
| Staples 3/8 in | 1 box | Insect screen |
Siding and trim
| Item | Qty | Used for |
|---|---|---|
| 5/8 in T1-11, 4×8 sheet | 15 | Walls (480 sq ft, before the door and window cut-outs) |
| 5/8 in T1-11, 4×8 sheet | 2 | Both gable triangles |
| 5/8 in T1-11, 4×8 sheet | 2 | Door leaves (one per leaf) |
| 1/2 in plywood, 4×8 sheet | 2 | Eave soffit and header fillers |
| Z-flashing, 10 ft | 2 | Wall siding to gable siding joint |
| Drip cap, 10 ft | 2 | Over the door and window head casings |
| 1×6 x 10 ft and 12 ft | 2 + 2 | Eave fascia (two 20′ 8″ runs, spliced) |
| 1×6 x 8 ft | 4 | Rake fascia (one 7′ 0 1/16″ piece per board) |
| 1×4 x 16 ft | 2 | Corner trim on the eave walls |
| 1×4 x 14 ft | 3 | Door casing sides, door stiles |
| 1×4 x 8 ft | 13 | Gable-wall corner trim, door head casing, door rails and Z braces, window casings |
| 1×2 x 8 ft | 2 | Door stop and astragal |
| Exterior paint and primer in one | 6 gal | Two coats over about 706 sq ft |
| Exterior caulk | 3 tubes | Trim |
Ramp
| Item | Qty | Used for |
|---|---|---|
| Pressure-treated 2×10 x 8 ft | 2 | Stringers (two tapered stringers from each board) |
| Pressure-treated 2×6 x 14 ft | 4 | 8 deck boards, 6′ 9″ each |
| Pressure-treated 2×4 x 8 ft | 2 | Ledger on the rim joist and skid, and a flat filler behind it |
| Exterior deck screws 3 in | 145 | Boards into the stringers |
| Structural screws 5 in, 1/4 in | 12 | Ledger into the rim joist and skid |
| Hook-and-eye latches, 4 in | 2 | Holding the ramp to its ledger |
| Anti-slip grit tape, 2 in x 15 ft | 4 rolls | One strip along each board |
Hardware and windows
| Item | Qty |
|---|---|
| Framing nails 3 1/2 in (16d), hot-dip galvanized (about 1,591 nails plus 10 percent) | 44 lb |
| Siding nails 2 1/2 in (8d), hot-dip galvanized | 18 lb |
| Sheathing nails 2 1/2 in (8d) for OSB | 9 lb |
| Connector nails 1 1/2 in for the ties | 4 lb |
| T-strap door hinges | 6 |
| Carriage bolts 1/4 x 2 in with washers and nuts | 18 |
| Door handle and latch set | 1 |
| Barrel bolts for the fixed leaf | 2 |
| Hold-open hook and eye, 6 in | 2 |
| Brush door sweeps, 36 in | 2 |
| Aluminum threshold cap, 6 ft | 1 |
| Exterior screws 1 1/4 in (door frame to T1-11, soffit vent flanges) | 1 lb |
| Exterior screws 3 in (hinge straps into framing) | 1 box |
| Structural wood screws 5 in, exterior (tight wall corners) | 18 |
| Prefabricated window, 36 x 36 in rough opening | 2 |
| Flashing tape 4 in | 1 roll |
| Wood shims | 1 bundle |
Cut list highlights
Most of the 10×20 cut list is square cuts: 52 wall studs at 7′ 6″ and 17 floor joists at 9′ 9″. The table holds the parts that need angles, splices or a tape for each piece.
| Part | Lumber | Cut length | Qty |
|---|---|---|---|
| Rafter (board length, see below) | 2×4 | 6′ 9 7/16″ | 32 |
| Fly rafter (rake) | 2×4 | 6′ 9 7/16″ | 4 |
| Ridge board (spliced) | 2×6 | 20′ 8″ | 1 |
| Ridge splice cleat (flat under the joint) | 2×4 | 2′ 0″ | 1 |
| Rafter tie (interior pairs, at the plates) | 2×4 | 10′ 0″ | 14 |
| Collar tie | 2×4 | 4′ 10 9/16″ | 7 |
| Lookout block (rake overhang) | 2×4 | 2 1/2″ | 16 |
| Frieze block (over the eave walls, top beveled) | 2×4 | 1′ 0 1/4″ to 1′ 1 3/4″ | 30 |
| Skid (spliced) | PT 4×4 | 20′ 0″ | 4 |
| Rim joist (spliced) | PT 2×6 | 20′ 0″ | 2 |
| Front and back wall plate (spliced) | 2×4 | 20′ 0″ | 4 |
| Front and back cap plate (spliced) | 2×4 | 19′ 5″ | 2 |
| Side wall plate | 2×4 | 9′ 4 3/4″ | 4 |
| Side wall cap plate | 2×4 | 10′ 0″ | 2 |
| Door header (2×8 doubled + 1/2 ply) | 2×8 | 6′ 3″ | 2 |
| Door trimmer | 2×4 | 6′ 4 1/2″ | 2 |
| Window header (2×6 doubled + 1/2 ply), per window | 2×6 | 3′ 3″ | 2 |
| Window trimmer, per window | 2×4 | 6′ 6″ | 2 |
| Center gable stud (under the ridge) | 2×4 | 2′ 2 13/16″ | 2 |
| Gable end studs | 2×4 | 7 1/16″, 11 1/16″, 1′ 3 1/16″, 1′ 7 1/16″, 1′ 11 1/16″, 2′ 3 1/16″, 2′ 7 1/16″ | 2 each |
| Gable corner nailer (flat on the cap plate under each end rafter) | 2×4 | 9 5/8″ | 2 |
| Gable vent sill and header (flat) | 2×4 | 2′ 6 1/2″ | 4 |
| Gable vent side stud | 2×4 | 1′ 0″ | 4 |
Rafters. Each rafter needs a 6′ 9 7/16″ board, measured along the board from the long point of the ridge plumb cut to the long point of the tail plumb cut, including the 12 in eave overhang. The top edge between the two plumb cuts is shorter, 6′ 7 11/16″, so do not lay out 6′ 9 7/16″ along the top edge. The list buys 14 ft 2x4s and cuts two rafters from each, which leaves about 5 in per board, so measure the board before you mark the second one. An 8 ft board holds only one rafter and wastes about 14 1/2 in, so you would need 32 boards instead of 16. Two more 14 ft boards give the 4 fly rafters, so the roof takes 18 of the 25 boards at 14 ft.
Mark the plumb cuts with a speed square pivoted to 6 on the common scale. The birdsmouth seat is 2 1/2 in, which makes the notch about 1 1/8 in deep. Keep the notch to a third of the rafter’s depth or less, so do not cut it any deeper. Cut one pattern rafter, test it at both ends and the middle of the shed, then trace the other 31.
The 4 fly rafters hang off the 2 1/2 in lookout blocks and the ridge extension, not a wall, so they get the plumb cuts but no birdsmouth.
Ridge. The ridge is 20′ 8″, not 20′ 0″, because it runs 4 in past each gable wall to carry the fly rafters. It is cut 9′ 8″ (116 in) from a 10 ft 2×6 and 11′ 0″ (132 in) from a 12 ft 2×6. The joint is centered on the rafter pair 9′ 4″ from the left corner, so both ends of the splice are nailed through rafters; hold it on the temporary 2×4 post until that pair is set, then nail the 2′ 0″ cleat under the joint.
The 20 ft runs. The skids, rim joists, wall plates, cap plates, ridge and eave fascia are all longer than the 16 ft stock on the list, so each is two boards with a planned joint. Each skid is one 8 ft and one 12 ft 4×4, with the joints of neighboring skids 4 ft apart, each joint under a floor joist and scabbed on both sides with a 3 ft treated 2×4 and six 3 1/2 in galvanized nails per scab. Counting from the front, skids 1 and 3 run 8′ 0″ then 12′ 0″ from the left end, and skids 2 and 4 run 12′ 0″ then 8′ 0″. Each rim breaks where a layout joist and a second joist sit side by side, so both rim ends nail into a full joist. Spliced skids work on a level, compacted pad but are weak for dragging, so do not plan to skid this shed to a new spot later.
The splices follow from buying no board over 16 ft, the longest length most home centers stock. If your yard sells 20 ft treated 4×4 and 2×6, one board per skid and rim removes those joints; recount the stock before you order.
Wall plates. The plan frames and raises the 20 ft front wall in two sections, so two people can lift each one: section 1 runs from the left corner to 13′ 4 3/4″ (about 180 lb) and section 2 from there to the right corner (about 90 lb). The bottom and top plates are each cut 13′ 4 3/4″ and 6′ 7 1/4″ so both break at the section joint, where a joint stud ends each section. The front cap plate is cut 6′ 6 1/4″ and 12′ 10 3/4″, so its joint lands on a stud 6′ 7″ from the section joint and ties the two sections together. The back plates break at 10′ 7 1/4″ from the right corner, a 10 ft and a 12 ft board with the joint on a stud, and the back cap plate uses a 16 ft board. The side walls get 9′ 4 3/4″ plates that drop in between the eave walls, and full 10 ft cap plates that lap the corners.
Headers. The 72 in door opening gets a doubled 2×8 header, two 6′ 3″ pieces cut from one 14 ft board with a 1/2 in plywood filler between them, on trimmers cut to 6′ 4 1/2″, with four 6 1/4″ cripples above it. The bottom plate is cut out of the doorway after the wall is up, so the door leaves swing over the floor. Each window gets a doubled 2×6 header (two 3′ 3″ pieces) on 6′ 6″ trimmers, two 6 1/2″ cripples above, a 3′ 0″ sill and two 3′ 4 1/2″ cripples below.
Gable studs. Each 10 ft gable has one 2′ 2 13/16″ center stud plus seven end studs, one each of 7 1/16″, 11 1/16″, 1′ 3 1/16″, 1′ 7 1/16″, 1′ 11 1/16″, 2′ 3 1/16″ and 2′ 7 1/16″. Four flat 2′ 6 1/2″ pieces and four 1′ 0″ side studs frame the two louvered vent openings. The studs are laid out 16 in on center from one corner so the T1-11 joints land on them. That means the two halves of a gable are not mirror images, so label each stud and measure it off your actual end rafter before cutting.
Gable vs lean-to: what changes
The gable column is the rebuilt plan. We also ran the same 10×20 footprint as a lean-to (single-slope) roof at 3/12, with an 80 in low back wall, the door in the high front wall and the window in the back wall. The skids and joists stay the same; the studs, rafters and siding change. The lean-to run is a reference build made before the re-issue, so its brace, stake and floor-sheet counts follow the older rules: add the plan’s extra decking sheet and braces if you build it.
| Item | Gable (6/12) | Lean-to (3/12) |
|---|---|---|
| Rafters | 32 2×4 at 6′ 9 7/16″ + 4 fly | 16 2×6 at 11′ 9 1/2″ + 2 fly |
| Ridge board | 2×6, 20′ 8″ from a 10 ft and a 12 ft board | None |
| Wall studs | 7′ 6″ on all four walls | 8′ 8 5/8″ front, 6′ 3 1/2″ back, stepped on the sides |
| 2×4 framing boards bought | 121 | 65 |
| 2×4 seam blocks, stakes, cleats, braces and posts | 33 | 11 |
| 2×6 boards bought (not treated) | 4 | 23 |
| T1-11 sheets | 19, all 4×8 | 18: seven 4×10, two 4×9, nine 4×8 |
| Roof OSB sheets | 11 | 9 |
| Shingle bundles | 11 | 9 |
| Felt | 1 roll | 2 rolls, laid double below 4/12 |
| Fascia | 1×6 | 1×8 |
| Extra hardware | 2 Z-flashing, 2 gable vents (12 x 12 in) | 4 twist straps at the wall corners |
| Framing nails (16d) | 44 lb | 28 lb |
| Floor | 4 skids, 17 joists, 8 sheets | 4 skids, 17 joists, 7 sheets |
On a 10 ft deep shed the lean-to rafters are 2×6: the span check compares 113 in against a 143 in limit for 2×6 at 30 psf, while a 2×4 tops out near 98 in. That is why the lean-to buys 23 plain 2x6s (16 rafters and 2 fly rafters from 12 ft stock, plus blocking and a header) but far fewer 2x4s. Each side wall has 9 studs stepping from 6′ 5 3/8″ to 8′ 9 1/4″ under a 9′ 8 1/2″ sloped top plate cut at 14 degrees.
Each lean-to rafter is 11′ 9 1/2″ from a 12 ft board, which leaves only about 2 1/2 in, so check the board ends before you mark it. The 8′ 8 5/8″ front studs come out of 10 ft boards, and the high wall takes 4×10 siding sheets, which some yards have to order. At 3/12, read the minimum slope on the shingle wrapper and follow the maker’s low-slope instructions. For single-slope layouts, see the 8×16 lean-to shed plan, all lean-to shed plans and our gable vs lean-to vs hip roof comparison.
Where the waste goes
- Wall studs: 90 in from a 96 in board leaves about 6 in each.
- Rafters: two 6′ 9 7/16″ rafters from a 14 ft board leave about 5 in, so there is little for blocking; the list already buys boards for the lookout blocks and short gable studs.
- Floor joists: 9′ 9″ from a 10 ft board leaves 3 in for squaring the ends.
- Rafter ties: the fourteen 10′ 0″ ties come from 12 ft boards, leaving about 2 ft each. The list buys 4 separate 8 ft boards for the twelve 24 in brace stakes, so these offcuts are spare blocking.
- Collar ties: two 4′ 10 9/16″ ties per 10 ft board leave about 2 7/8 in.
- 20 ft runs: the skids use full boards with factory ends and no offcut. The rim and back plate pieces leave about 7 1/4 in and 16 3/4 in, the front plate pieces about 7 1/4 in each from the long boards and 9 1/2 in from the 14 ft board that gives both short pieces, and the ridge and eave fascia pieces about 4 in and 12 in.
- Cap plates: the front cap pieces leave about 13 1/4 in (12′ 10 3/4″ from 14 ft) and 17 3/4 in (6′ 6 1/4″ from 8 ft).
- Side cap plates: each uses a full 10 ft board with no trim room, so check that the factory ends are square at the yard.
- Floor decking and wall siding: 8 floor sheets give 256 sq ft for a 200 sq ft floor, because a tongue and groove sheet covers only about 47 1/2 in once its tongue sits in the next one, and 15 wall sheets give 480 sq ft for 480 sq ft of wall, so the walls have no spare. The floor leftover is in strips you cannot use for a full panel, so a damaged sheet still means a trip back to the yard.
- Spares: the counts include nothing for rejects. The plan says to add 2 or 3 spare studs for bad boards, so pick straight stock at the yard.
The 16 ft pieces are one back cap plate board, four 4×6 pad frame boards and the two corner trim boards for the eave walls. Everything else is 8, 10, 12 or 14 ft stock.
Tools for a 10×20 build
- Circular saw, speed square and framing square for 52 stud cuts and 36 rafters; cut the 2 1/2 in lookout blocks from a long clamped stick with a stop block, never as loose scraps
- Framing hammer or framing nailer, and a drill/driver for the screws
- 4 ft level, 25 ft tape for checking that the floor diagonals both read 22′ 4 5/16″ and the pad frame diagonals 25′ 0 3/4″, and a string line for the 20 ft rims and plates
- A hand tamper or a rented plate compactor for 4.7 cu yd of gravel, laid in thin layers
- A crew of two: the 20 ft walls go up in two sections each, the heaviest being the front wall’s at about 180 lb as a bare frame (back sections about 130 and 110 lb, side walls about 150 lb), and the nailed floor frame weighs about 450 lb, so build it in place on the skids
- Safety glasses and hearing protection for the saw and nailer, and gloves for the treated lumber
Common mistakes
- Mixing up 10×20 and 20×10. In this list the ridge runs along the 20 ft side and the door sits in a 20 ft wall. If the ridge runs the 10 ft way, the roof spans 20 ft and each rafter’s run grows from about 60 in to about 120 in, past the 2×4 span check, and the ridge, gables and rafter sizes all change.
- Lining up the splices. Every 20 ft member here is two boards. If the skid, rim, plate and cap plate joints all fall at the same spot, the floor and walls get a hinge line. Keep them where the list puts them.
- Forgetting the door sheets. The siding cut out of the doorway is 76 1/2 in tall, shorter than the 77 1/4 in door leaf, so each leaf needs its own new T1-11 sheet.
- Skipping rafter ties. A ridge board is not a beam. The 14 rafter ties at the plates stop the 20 ft walls from spreading. The 7 collar ties, on every other pair in the upper third, hold the rafter pairs together near the ridge; they do not replace the rafter ties.
- Deep birdsmouths. A full 3 1/2 in seat would notch a 2×4 rafter past the one-third limit, so keep the seat at 2 1/2 in.
- Swapping materials without recounting. This list is for 3-tab shingles and T1-11. Architectural shingles, metal roofing or lap siding cover differently, so recount from the coverage printed on the bundle or the maker’s install guide.
- Untreated wood near the ground. Skids, rims, joists and the ramp are pressure treated; plain framing lumber there rots. Use ground-contact rated wood for the skids, pad frame and ramp, and hot-dip galvanized nails and treated-lumber rated screws in treated wood. The USDA Wood Handbook covers why wet, untreated wood decays.
Whether a 200 sq ft shed needs a permit, and what setbacks and tie-downs apply, varies by town, so check your local permit office before you order. Our shed permit checklist lists what to ask. The list includes 8 screw-in ground anchors with straps; ask the same office which anchor type your area accepts for a skid shed.
For how to read any list like this one, see our shed material list guide. For other sizes, try the shed material calculator. For the base under the skids, see shed foundation options, and for a rough budget, see how much it costs to build a shed.
Get the full plan
The 10×20 gable shed plan is a 74-page 3DSHEDPLANS PDF with 28 sections, the cut list, the cutting plan and the printable material list above, for a 72 in double door, two 3×3 ft windows and a wheel-in ramp, at about 80 hours for two people. For the nearest sizes, see the 12×20 gable shed plan, the 8×20 gable shed plan and the 10×24 gable shed plan, or compare the 12×20 shed material list and the 10×16 shed material list.
Want to see the format first? Download the free 10×20 gable shed plan preview PDF. Need more or less room? Compare all gable shed plans or browse every size on the shed plans page.
Frequently asked questions
What is on a 10×20 shed material list?
For the 3DSHEDPLANS 10×20 gable shed with a 6/12 roof and a 72 in double door, the plan lists 154 2x4s, 25 treated 2x6s, 8 treated 4x4s, 8 sheets of 3/4 in plywood, 11 of OSB, 19 of T1-11, 2 of 1/2 in plywood and 11 shingle bundles, plus the ramp, pad frame, anchors and trim.
How many 2x4s do I need for a 10×20 shed?
154 in all for the 10×20 gable shed with a 72 in double door and two windows. That is 121 framing boards (63 at 8 ft, 15 at 10 ft, 17 at 12 ft, 25 at 14 ft, 1 at 16 ft), plus 33 for floor seam blocks, 22 temporary braces, the ridge post, brace stakes and deck cleats.
How many sheets of plywood, OSB and siding does a 10×20 shed need?
8 sheets of 3/4 in tongue and groove plywood for the floor, 11 sheets of 7/16 in OSB for the roof, 19 sheets of 5/8 in T1-11 for the walls, gables and door leaves, and 2 sheets of 1/2 in plywood for the soffit and header fillers.
How many bundles of shingles for a 10×20 shed roof?
11 bundles of 3-tab shingles for the 6/12 gable roof, which covers the 12 in eave and 4 in rake overhang. The count includes the starter course, the ridge cap and about 10 percent extra.
Are there free 10×20 shed plans with a materials list?
This page is a free 10×20 materials list with cut lengths. The 3DSHEDPLANS 10×20 gable shed plan is a 74-page PDF with 28 sections, the cutting plan and this same list, and a free 10×20 preview PDF shows the format before you buy.
Shed building guides
- 10×16 Shed with Porch Material List: Lumber and Hardware
- 8×20 Firewood Shed Material List: Lumber, Slats, Hardware
- 8×8 Lean-To Shed Material List: Lumber, Sheets, Hardware
- 8×8 Hip Roof Shed Material List: Lumber, Sheets, Hardware
- 8×20 Lean-To Shed Material List: Lumber, Sheets, Hardware
- 8×20 Hip Roof Shed Material List: Lumber, Sheets, Hardware