Gable pavilion · 192 sq ft
12X16 Backyard Pavilion Plan
Build this 12x16 gable pavilion yourself. Every board, cut and step, drawn in 3D.
Free preview: the build stages in 3D. The full plan adds every measurement, the material list and the cut list.
- 30-day money-back guarantee
- PDF by email right after checkout
- Visa, Mastercard, Amex, PayPal
- Full material and shopping list
- Cut list with every length
- Step-by-step 3D views
- Phone, tablet, PC and Mac

The 3DSHEDPLANS™ 12x16 backyard pavilion plan is a 43-page PDF for an open-sided gable pavilion 16 ft by 12 ft to the outside of the posts, with 8' 0" of clear height under the beams and a 6/12 shingled roof on six 6x6 posts set in concrete. It has a shopping list, a cut list and 12 step-by-step sections.
Get the full plan PDF for $19.99 or download the free preview
What builders say
Pre-built sheds were hundreds of dollars. The plan laid everything out perfectly, and I saved hundreds in the process.
I worked as a joiner's assistant for three years and was skeptical. The plan was well laid out and beautifully illustrated.
A project for me and my son. The plan arrived in my email almost instantly, and everything we needed was included.
12×16 pavilion plans: what you get
These 12×16 pavilion plans are for a freestanding backyard pavilion 16 ft along the beams and 12 ft across (192 sq ft to the outside faces of the posts), with a shingled gable roof that keeps the sun and the rain off a table, a grill corner or a seating group. The PDF has 43 pages: a shopping list by building stage, a cut list with every length and the boards to buy, and 12 step-by-step sections with measured drawings and 3D views, from the batter boards to the ridge cap.
The frame is built the way timber pavilions have been built for a long time: 6 treated 6×6 posts stand 4 ft deep in concrete, a two-board 2×12 beam sits in a notch on each long side, and a bent stands on every post line, with a two-board tie beam that clamps the rafter feet. Knee braces stiffen the frame both ways. The roof is a 6 in 12 pitch with 1′ 0″ overhangs all around, a plywood deck and laminated shingles.
Every part in the lists is drawn on its step page, and the shopping list, the cut list and the drawings were checked against each other part for part. The 12×16 backyard pavilion plan sells for $19.99 as an instant PDF download that works on a phone, a tablet or a printed copy.
12×16 backyard pavilion specs
Every number below comes from the plan’s own specs page. Lumber sizes are nominal: a 2×6 is really 1 1/2 in by 5 1/2 in, and a 6×6 post is 5 1/2 in square.
| Spec | Value |
|---|---|
| Footprint | 16′ 0″ x 12′ 0″ to the outside faces of the posts (192 sq ft) |
| Roof | 18′ 0″ x 14′ 3″ including the overhangs and fascia, 6 in 12 pitch |
| Clear height | 8′ 0″ from grade to the underside of the beams |
| Overall height | about 12′ 4 3/4″ from grade to the top of the ridge shingles |
| Posts | 6 treated 6×6 posts, 14 ft long, rated for ground contact (UC4B), 4′ 0″ in concrete |
| Footings | 1′ 8″ round at the corners, 2′ 0″ at the middle posts, 4′ 6″ deep with 6″ of gravel under the post |
| Beams | two 2×12 boards per side in a notch on each post, bolted through |
| Bents | 3 bents: 2×10 tie beam boards at the two end bents, 2×8 at the middle bent, a 4×6 timber king post at each end |
| Rafters | 2×6, 9 pairs at 1′ 11 5/16″ on center, 6 rafter ties (2×8), a fly rafter at each gable edge |
| Ridge | 2×8 ridge board in two lengths |
| Knee braces | 16 treated 4×4 braces at 45 degrees, lapped on the posts, plus 4 seated under the beams at the middle posts |
| Roofing | 3/4 in exterior plywood, synthetic underlayment, drip edge, laminated shingles, ridge cap |
| Space inside the posts | 15′ 1″ along the beams by 11′ 1″ across |
| Not included | a floor or slab, walls or screens, electrics and lights |
| The PDF | 43 pages, 12 step-by-step sections |
Posts set in concrete, and the footings
The pavilion stands on 6 treated 6×6 posts, each 14 ft long and tagged for ground contact, heavy duty (UC4B). Each post goes 4′ 0″ into the ground. The corner holes are 1′ 8″ across and the middle ones 2′ 0″, because the middle posts carry half the roof, dug 4′ 6″ deep so 6″ of tamped gravel sits under the post. Two 1/2 in rebar pins go through the buried end of every post, so the concrete locks it in, and the top of the concrete is crowned 1 1/2″ above grade so water runs off.
The plan does not trim posts in the air. Each uncut post is stood in its hole first, and one laser line marks every shoulder at the same height. Then the post comes out, is cut and notched on sawhorses, and goes back on the same gravel. The finished posts are 12′ 11 1/4″ from the bottom end to the top, and the buried end is never cut, so it keeps its factory treatment.
The concrete takes 130 bags of 60 lb mix (19 bags per corner hole and 27 per middle hole). For that much, a ready-mix truck or a rented towable mixer saves a day. Frost depth differs from town to town: ask your local permit office how deep your footings must go, and if it is deeper than the plan, the holes go deeper and the posts get longer.
Beams and bents
A beam of two 2×12 boards runs along each long side. Each post has a 3″ deep notch cut on its outside face, and both boards bear on that shoulder, so the bolts only hold them in place. The boards break over the middle post’s center, where two steel straps tie the ends together. The plan has 8 beam boards, each 9′ 0″ long, from 10 ft stock, nailed together and bolted through each post.
Across the pavilion, a bent stands on each of the 3 post lines. A bent is a tie beam of two boards 12′ 0″ long with the rafter pair for that line clamped between them, on 1/2 in plywood spacers. Two bolts pass through the whole stack at each rafter foot, and a notched saddle block hooked over the beam stops the tie beam sliding outward. The two end bents use 2×10 tie beam boards and carry a 4×6 timber king post, 2′ 0 7/8″ tall, that holds the ridge in a notch, with two struts beside it. The middle bent uses 2×8 tie beam boards.
This is a real tied roof: the tie beams and rafter ties hold the rafter feet together, so the roof does not push the beams outward. That is why the plan can use a plain 2×8 ridge board instead of a large structural ridge beam.
Knee braces that keep the frame square
An open pavilion has no walls to stop it swaying, so knee braces do that job, together with the posts set deep in concrete. The plan has 16 treated 4×4 knee braces at 45 degrees, each 4′ 11 3/8″ long to the long points: one along the beam at each corner and one on each face of every bent. Each brace laps the post and the beam or tie beam and is held with two bolts and two structural screws at each end. Under the beams at the middle posts, 4 more braces are seated tight between the post and the beam, each 4′ 0 1/16″ long, held with structural screws.
Where a brace meets another on the far face of a bent, the same long through bolts pass through both braces and the tie beam. Every 45 degree cut is drawn with its long point, and the shopping list adds one spare 4×4, because an angled cut is the likeliest miscut in the build.
Mind the head room: right at a post the braces come down to about 5′ 0 1/2″ above grade. Beside a middle post the seated braces come down to 5′ 2″ under the beam. The plan has a drawing and a table of where full head room starts in each opening, so you can keep the walkway and the grill in the middle of an opening.
Rafters and the ridge
The roof has 9 rafter pairs of 2×6 at 1′ 11 5/16″ on center, equal bays with a pair on every post line, 18 rafters in all plus 4 fly rafters at the gable edges. Each rafter is 7′ 9 1/16″ along its top edge, cut from a 10 ft board. You cut one pattern rafter first, check it on the beam, and trace every other rafter from it.
Each rafter sits on the beam with a level seat and a short plumb heel, and its top lies flat on the 2×8 ridge board. The inner pairs each get a 2×8 rafter tie on the beam tops, 6 ties in all, bolted at both ends, and a hurricane tie holds each inner rafter down to the beam. The roof pitch is 6 in 12, a common slope for shingles that sheds rain and looks right on a backyard building.
Roof deck and shingles
The roof is 18′ 0″ by 14′ 3″ with the overhangs and the 2×6 fascia, so it shades more than the footprint. It is decked with 12 sheets of 3/4 in exterior plywood (4 by 8 ft), which also looks good from below because the underside of the deck is what you see when you sit under it. The deck nails go 6 in apart on the edges and 12 in in the field.
On top go 8 pieces of galvanized drip edge, synthetic underlayment, a starter strip, 10 bundles of laminated shingles and a bundle of ridge cap. The plan shows the order: drip edge on the eaves first, underlayment over it, drip edge on the rakes over the underlayment, then the shingles from the eave up. A shingle roof is quiet in the rain and matches the roof on most houses.
The lift plan: crew, weights and working at height
Every part of this pavilion goes up by hand, and nothing depends on a rope lift. The plan is written for three people. The heaviest part is an uncut post, about 161 lb, which three people stand in its hole. Then come a tie beam board (about 64 lb) and a beam board (about 58 lb), which go up one board at a time, one person on a ladder at each post and one on the ground passing the board up. The rafters go up one at a time, about 25 lb each, and the long ridge board is about 41 lb.
From the beams up the work is overhead: the beam tops are 8′ 11 1/4″ above grade and the ridge 12′ 3 1/2″. The safer way is two sections of rented frame scaffold with planks and guardrails, or a rolling tower, set inside the frame. With ladders only, the plan says where each ladder stands for each lift, always inside the frame on firm ground or a plywood pad. Never stand above the third rung from the top, never climb carrying a board, and stay off the roof deck in wet or windy weather.
The PDF has a time table for a crew of three: about 59 hours in all, or four or five weekends for a first-timer, plus two days for the concrete to cure before the beams go up.
What a backyard pavilion is good for
The space inside the posts is 15′ 1″ along the beams by 11′ 1″ across. That suits a dining table for six to eight or a seating group, with the roof overhang shading the edges as well. Here are the common uses, kept general because every yard is different:
- Patio cover. Shade for a table on a patio, gravel or the lawn. The posts stand in the ground as built, and you can add a floor of pavers or gravel afterwards.
- Grill or outdoor kitchen corner. Keep the grill in the middle of an opening, clear of the knee braces, and follow your grill maker’s clearances to wood and to the roof above.
- Hot tub cover. A tub needs its own base that carries its weight; this plan does not cover a slab or a deck. Check the tub maker’s clearances and the electrical needs with an electrician.
- Garden or pool shade. A shaded spot to sit out of the sun, with open sides for the breeze.
The roof keeps off rain falling straight down. Driving rain still blows in at the open sides, so it is a shade and shelter roof, not a room.
Materials list for the 12×16 backyard pavilion
The plan’s shopping list has 45 items, grouped by building stage so each stage has its parts, and every board is listed in the stock length that wastes the least. Every piece of lumber that stays in the pavilion is pressure-treated. In short, this is what you buy:
- Posts: 6 treated 6×6 posts rated for ground contact, plus end-grain sealer
- Treated framing lumber: 63 boards for the beams, bents, knee braces, rafters, ridge and fascia, spares for the likeliest miscuts included
- Footings: 130 bags of 60 lb concrete mix, 19 bags of gravel and 12 rebar pins
- Roofing: 12 sheets of plywood (4 by 8 ft), 10 bundles of laminated shingles, 8 pieces of drip edge, underlayment, starter strip and ridge cap
- Bolts and connectors: 95 galvanized carriage bolts with washers and nuts, 22 hurricane ties, structural screws, nails and the plywood spacers
- Temporary and finish: 16 2x4s and stakes for the layout and the post braces, and 4 gallons of exterior stain
The full list of all 45 items, with the cut list, is in the plan PDF.
The plan does not list prices because lumber costs change every week. Take the list to the pro desk of your lumber yard or home center for a quote, and order the ground-contact posts a week or two ahead.
Tools and rentals
Most of the tools are common framing tools. The rentals are the auger for the holes and, if you can, scaffold for the overhead work; a laser level makes the shoulder marks on every post quick and exact.
- Circular saw with a rip guide, a handsaw or reciprocating saw, and a miter saw if you have one
- Speed square, framing square, chisel and mallet for the post notches
- Drill/driver with 9/16 in and 5/8 in long bits for the bolt and pin holes
- Socket set with a 3/4 in socket and a framing hammer
- Towable auger (rental), a clamshell digger and a digging bar for the holes
- Rotating laser level or water level, a post level, string line and a plumb bob
- Two sections of rented frame scaffold or a rolling tower (recommended), or three step ladders
- A 12 ft extension ladder, sawhorses and four clamps that open at least 14 in
- Utility knife with hook blades, tin snips and a roofing hammer or coil roofing nailer
- Safety glasses, ear protection, gloves, a dust mask and a hard hat
Use hot-dip galvanized fasteners and connectors, or screws rated for treated lumber: plain steel corrodes in it. Never burn treated scraps; the smoke and ash are toxic.
How to build the 12×16 backyard pavilion, step by step
The PDF splits the build into 12 step-by-step sections, each with numbered steps, measured drawings and a 3D view with the new parts in orange. This is the order the plan follows, with the typical time for a crew of three from the plan’s time table:
Step 1: Layout and holes (about 8 hours)
Set batter boards, stretch the strings 16′ 0″ by 12′ 0″, make the two diagonals equal, then dig each hole 4′ 6″ deep and tamp the gravel.
Step 2: Posts (about 8 hours)
Stand every post in its hole, mark the shoulders with one laser line, lift them out, cut and notch them on sawhorses, pin them, set them back, plumb and brace them and pour the concrete.
Step 3: Beams (about 4 hours)
Lift the 2×12 boards onto the shoulders one at a time, nail the two boards of each side together and bolt them through the posts.
Step 4: Bents and knee braces (about 8 hours)
Cut the pattern rafter, build each bent on the beam tops with its spacers, fillers and saddle blocks, stand the king posts and struts, then bolt on the knee braces.
Step 5: Ridge, rafters and rafter ties (about 8 hours)
Drop the ridge into the king post notches, set the rafters one at a time, bolt the rafter ties and nail the hurricane ties.
Step 6: Fly rafters and fascia (about 3 hours)
Hang the fly rafters at each gable edge and nail the fascia across the rafter tails.
Step 7: Roof deck (about 4 hours)
Nail the plywood deck to the rafters, staggering the joints.
Step 8: Roofing (about 10 hours)
Drip edge, underlayment, the starter strip, the shingles and the ridge cap.
Step 9: Finish and care (about 6 hours)
Stain the frame once the treated wood is dry enough to take it.
The skill level is careful framing: measuring, square and angled cuts, drilling straight bolt holes and checking level and plumb. The posts and the overhead lifts need three people, and the plan says who does what at each lift.
Where to put a pavilion
- Room for the roof. The roof is 18′ 0″ by 14′ 3″. Pick a spot with no tree limbs or wires over it and about 6 ft of working room outside the posts for ladders.
- Distance and permits. A roofed structure this size often needs a permit, and towns set how far it must stand from the property lines and the house. Check your local permit office before you buy anything.
- Buried lines. Call 811 a few days before you dig, so gas, power and water lines get marked.
- Sloped ground. The ground need not be flat. Each post is marked where it stands, so the beams come out level; the plan says how much slope the post length allows.
- Which way it faces. The long sides are the open sides under the eaves. Face one toward the view or the house, and put the gable ends toward the strongest wind if you have the choice.
- Drainage. Avoid low spots where water stands after rain; the crowned concrete sheds water from the posts, but the ground around them should drain too.
What is in the free 12×16 backyard pavilion plan preview?
Download the free 12×16 backyard pavilion plan preview before you buy. It shows the pavilion from the front and the back, the build stages in order and real pages from the plan, so you can see how the drawings look and whether the size fits your yard.
| Item | Free preview | Full plan |
|---|---|---|
| Overview, views and build stages | Yes | Yes |
| Shopping list with quantities | No | Yes |
| Cut list for every part | No | Yes |
| Measurements in every step | Overall sizes | Every part |
| Step-by-step drawings | Preview pages | 43 pages, 12 sections |
| Joint close-ups, lift plan and time table | No | Yes |
| Price | Free | $19.99 |
Not right for you? Email [email protected] within 30 days of your purchase for a full refund.
Before you build
Rules for roofed backyard structures (permits, height, distance to property lines, footing depth) vary by town and HOA, and so do the snow and wind a roof must carry. The PDF lists what the frame was laid out for; it is not a certified rating. Check your local permit office before you buy lumber, and ask a local builder if anything is unclear.
The sides stay open. Do not add walls, screens or a solid rail to this frame: closed sides catch the wind in a way this frame is not laid out for. Set every post in its footing as shown, not on surface brackets or short piers; the posts in concrete and the knee braces together hold the frame square.
Every year, check the shingles and the drip edge, look over the bolts and tighten any that the drying wood has loosened, and keep the concrete crowns clear so water runs off the posts. More plans are on the all plans page.
Frequently asked questions
How big is the 12×16 pavilion?
It is 16' 0" by 12' 0" to the outside faces of the posts, with a 18' 0" by 14' 3" roof, 8' 0" of clear height under the beams and about 12' 4 3/4" to the top of the ridge.
How deep do the posts go?
Each 6×6 post stands 4' 0" deep in concrete on 6" of gravel, with two rebar pins through its buried end. If your frost line is deeper, the holes and posts get longer.
How many people do I need to build it?
Three. The heaviest part is an uncut post, about 161 lb. Beams, tie beams and rafters go up one board at a time. The plan's time table adds up to about 59 hours.
Can I put a hot tub or a grill under it?
Yes, with care. A hot tub needs its own base, which this plan does not cover. Keep a grill in the middle of an opening and follow the grill maker's clearances to wood and to the roof.
Do I need a permit for a 12×16 pavilion?
Rules for roofed backyard structures vary by town and HOA. Check your local permit office before you build, and call 811 before you dig.
More about the 12×16 gable pavilion plan
Inside the 12×16 backyard pavilion plan PDF
The 43-page PDF follows the build from start to finish, with 12 step-by-step sections. These are its parts in print order:
- How to use this plan: how to read the drawings, nominal and actual lumber sizes, the weight of the heaviest parts, safety at height and a time table for a crew of three.
- Overview and dimensions: views from the front and the back, the front and side elevations, every part named on the end of the pavilion and the main parts at a glance.
- Specs: footprint, roof size, clear height, overall height, posts, footings, beams, bents, rafters, roof deck and knee braces, and what the frame was laid out for.
- Permits and siting: what to ask before you dig (check your local permit office), calling 811, room for the roof and the ladders, sloped ground, which way it faces and where the knee braces leave full head room.
- Shopping list by section: every item with its quantity and what it is used for, grouped by building stage, with notes on buying ground-contact posts.
- Cut list: every part with its lumber, exact length, the boards to buy and how many parts each board gives.
- Tools and fasteners: the tool and rental list and a fastener schedule for every joint.
- Key joints up close: close-up pictures of every joint, from the post in its footing to the fly rafter.
- Layout and holes: batter boards, strings, the two equal diagonals, the hole sizes and the gravel bed.
- Posts: dry-fit in the hole, one laser line for every shoulder mark, cut and notch on sawhorses, rebar pins, concrete.
- Beams: working at height, the two-board beams on the notches, nails, bolts and straps.
- Bents: the pattern rafter, the tie beam boards, spacers, fillers, saddle blocks, king posts and struts.
- Knee braces: the lapped braces on the posts and the beams or tie beams, bolts and structural screws.
- Ridge and rafters: the ridge in the king post notches, every rafter traced from the pattern, rafter ties and hurricane ties.
- Fly rafters and fascia: the outer rafters at each gable and the fascia across the rafter tails.
- Roof deck: the plywood deck, nailed on the edges and in the field.
- Roofing: drip edge, underlayment, starter strip, laminated shingles and the ridge cap.
- Finish and care: stain once the treated wood has dried, and what to check every year.
- Build checklist: one line per stage to tick off as you go.
- How this plan was checked: what was cross-checked in the measurements, the drawings and the lists.
- Appendix: glossary: every carpentry word in the plan, in plain English.
Ready to build the 12×16 gable pavilion?
$19.99 for the full PDF: every step, cut and board. 30-day money-back guarantee.